Time and Work
Never add days. Make the total work the LCM of the days, turn each person into units-per-day, then add those.
Why this topic matters
If A paints a wall in 10 days, then in one day A paints one tenth of it. Time and work is about per-day work, because per-day work can be added.
2 or 3 questions in most papers. Days cannot be added; work per day can. The LCM method from Easy Maths turns every question into whole numbers.
Work per day, and the LCM total
If A takes a days, A does 1/a of the job per day. Working together, rates add: 1/a + 1/b.
Faster: let the total work be the LCM of the days. Then each person does a whole number of units per day.
- Total = LCM(12, 18) = 36 units. A does 3/day, B does 2/day.Whole numbers, no fractions.
- 4 days together: 4 × 5 = 20 units done.
- Left: 16 units. B alone: 16 / 2 = 8 days.
- 8 more days.
Efficiency
'A is twice as efficient as B' means A does twice the work per day, so A takes half the time.
If A is x% more efficient than B, A's rate = B's rate × (1 + x/100), so A's time = B's time / (1 + x/100).
- Rates 2 : 1. Together 3 units a day.Efficiency is work per day.
- Total = 3 × 14 = 42 units.
- A alone: 42 / 2 = 21 days.
Men, days and hours
The amount of work = number of workers × days × hours per day. If the job is the same, that product is the same.
If the job changes, divide by the work: M1 D1 H1 / W1 = M2 D2 H2 / W2.
- 12 × 8 × 10 = 16 × 6 × D.Same job, so the same total man-hours.
- 960 = 96 D, so D = 10.
Alternate days
If A and B work on alternate days, treat one pair of days as a block. Work in a block = A's rate + B's rate.
Fill whole blocks, then finish the remainder carefully day by day (whoever's turn it is).
- Total 30 units. A 3/day, B 2/day. One 2-day block = 5 units.
- 5 blocks = 10 days = 25 units. Left 5.
- Day 11 (A): 3 units, left 2. Day 12 (B): 2 units, done.Check whose turn it is after the blocks.
- 12 days.
Formula summary
Shortcuts and tricks
LCM method
Use it when: Three or more people, or pairs.
- A 10, B 15, C 30 → total 30 units.
- Rates 3, 2, 1 = 6 a day.
- 30/6 = 5 days.
- 30 units, 6 per day.
Alternate days
Use it when: A and B work on alternate days.
- Units per 2-day cycle.
- Run full cycles, then finish the leftover with whoever is next.
- 36 units. A 3, B 2 → 5 per cycle.
- 7 cycles = 14 days, 35 units.
- Day 15: A needs 1 unit = 1/3 day.
Common mistakes
Before you move on, you should be able to...
- add rates, not days
- set the job to the LCM of the days
- use M × D × H = constant
- solve alternate-day questions with blocks
Practice questions (11)
Try each one before opening the solution. Or practise them one by one so your score is saved.
easy A can do a job in 12 days, B in 18. Together?
- 36/5.
Answer: 7.2 days
easy 12 men working 8 h a day finish in 18 days. How many days for 16 men at 9 h a day?
- 12 × 18 × 8 / (16 × 9).
Answer: 12 days
medium A+B do a job in 12 days, B+C in 15, C+A in 20. How long for A alone?
- Work 60. Rates 5, 4, 3. A+B+C = 6.
- A = 6 - 4 = 2 → 30 days.
Answer: 30 days
medium A takes 20 days, B 30. They start together, but A leaves 5 days before the end. Total days?
- (T - 5)/20 + T/30 = 1 → 5T = 75.
Answer: 15 days
medium A is twice as good as B; together they finish in 14 days. A alone?
- Rates 2 and 1 = 3 per day, work 42.
- 42/2 = 21.
Answer: 21 days
hard 10 men finish a job in 15 days; 15 women finish it in 12. How many days for 5 men and 6 women?
- Work = 150 man-days = 180 woman-days, so 1 man = 1.2 women.
- 5 men + 6 women = 12 women → 180/12 = 15 days.
Answer: 15 days
hard A is 50% more efficient than B. Together they finish in 18 days. A alone?
- Rates 3:2, 5 units a day, work 90.
- 90/3.
Answer: 30 days
hard 20 men can finish a job in 30 days. After 10 days, 5 men leave. How many more days to finish?
- Work 600 man-days, 200 done.
- 400 / 15 men.
Answer: 26 2/3 days
hard 2 men and 3 women finish a job in 10 days; 3 men and 2 women in 8 days. How long for 2 men and 1 woman?
- Man = 7/200, woman = 1/100 per day (solve the two equations).
- 2 men + 1 woman = 16/200 = 2/25 → 12.5 days.
Answer: 12 1/2 days
hard A takes 6 days, B 8 days; with C they finish in 3 days. The fee is Rs 3,200. C's share?
- In 3 days A does 1/2, B does 3/8, so C does 1/8.
- 1/8 of 3200.
Answer: Rs 400
hard A takes 10 days, B 15. They work together, but A leaves after 2 days. How many more days does B need?
- 2 days together = 2 × 1/6 = 1/3.
- B does 2/3 at 1/15 a day.
Answer: 10 days
Class plan (2 hours, for trainers)
A tested order for teaching this topic in one 2-hour session. Present mode follows the same order.
| 10 min | Warm-up. |
| 25 min | Rates and the LCM total; together; one leaves. |
| 20 min | Efficiency. |
| 20 min | Men-days-hours. |
| 15 min | Alternate days. |
| 25 min | Practice set. |
| 5 min | Recap. |