Never add days. Make the total work the LCM of the days, turn each person into units-per-day, then add those.
If A paints a wall in 10 days, then in one day A paints one tenth of it. Time and work is about per-day work, because per-day work can be added.
2 or 3 questions in most papers. Days cannot be added; work per day can. The LCM method from Easy Maths turns every question into whole numbers.
If A takes a days, A does 1/a of the job per day. Working together, rates add: 1/a + 1/b.
Faster: let the total work be the LCM of the days. Then each person does a whole number of units per day.
A can do a job in 12 days, B in 18 days. They work together for 4 days, then A leaves. How long does B take to finish?
Answer: 8
'A is twice as efficient as B' means A does twice the work per day, so A takes half the time.
If A is x% more efficient than B, A's rate = B's rate × (1 + x/100), so A's time = B's time / (1 + x/100).
A is twice as efficient as B. Together they finish a job in 14 days. How long would A take alone?
Answer: 21
The amount of work = number of workers × days × hours per day. If the job is the same, that product is the same.
If the job changes, divide by the work: M1 D1 H1 / W1 = M2 D2 H2 / W2.
12 men working 8 hours a day finish a job in 10 days. How many days will 16 men working 6 hours a day take?
Answer: 10
If A and B work on alternate days, treat one pair of days as a block. Work in a block = A's rate + B's rate.
Fill whole blocks, then finish the remainder carefully day by day (whoever's turn it is).
A can do a job in 10 days and B in 15. They work on alternate days, starting with A. In how many days is the job done?
Answer: 12
Use it when: Three or more people, or pairs.
A 10 days, B 15, C 30 together?
Answer: 5 days
Use it when: A and B work on alternate days.
A 12 days, B 18 days, alternate, A starts.
Answer: 14 1/3 days
A+B do a job in 12 days, B+C in 15, C+A in 20. How long for A alone?
Answer: 30 days
A takes 20 days, B 30. They start together, but A leaves 5 days before the end. Total days?
Answer: 15 days
A is twice as good as B; together they finish in 14 days. A alone?
Answer: 21 days
10 men finish a job in 15 days; 15 women finish it in 12. How many days for 5 men and 6 women?
Answer: 15 days
11 questions with full solutions.